Subject:
|
Acceptance of Proposed Construction Delivery Method for Elementary School #17 and the New Crowley High School
|
District Goals:
|
Goal 1 Thriving Students Goal 2 Engaged Community Goal 3 Empowered Staff
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
The Texas Government Code provides six delivery methods for the procurement of constructions services. Administration is proposing the Construction Manager at Risk Delivery Method for Elementary #17 and the New Crowley High School. The Construction Manager at Risk is a delivery method used by Crowley ISD in past construction projects and is the only delivery method allowed by the Texas Government Code with a Guaranteed Maximum Price.
|
Budgetary Impact:
|
Funding for Elementary #17 and the New Crowley High School will be from voter-approved 2023 Bond dollars.
|
Recommendation:
|
Recommend approval of the Construction Manager at Risk delivery method for the Elementary #17 and new Crowley High School facilities as presented.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Randy Reaves - Executive Director of Operations
|
|
Signed By:
|
|
Michael McFarland - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Daryl Davis Moved, Member Kelicia Stevenson seconded to approve the Original motion 'Recommend approval of the Construction Manager at Risk delivery method for the Elementary #17 and new Crowley High School facilities as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0. | The motion Carried 7 - 0 | | | June Davis | Yes | Mia Hall | Yes | Gary Grassia | Yes | LaTonya Mayfield | Yes | Nedra Robinson | Yes | Kelicia Stevenson | Yes | Daryl Davis | Yes | |
|
|
|
|
|
|