Meeting Date:
|
|
Category:
|
Consideration and Possible Action Item(s) |
|
|
Type:
|
|
Subject:
|
Early Electrical Package for Crowley ISD Elementary #16 |
|
|
District Goals:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
The early electrical package for Elementary School #16 in the Karis development consists of the main electrical service switchgear, sub-distribution switchboards, and all panelboards that will be needed for the project. Also, in an effort to mitigate anticipated lead times due to supply chain issues and to facilitate early ordering of the electrical equipment, it is also necessary to include the mechanical equipment (packaged rooftop units, split systems and fans)in the early package so that the electrical breakers required for this equipment can be coordinated. |
|
|
Budgetary Impact:
|
$1,430,296 To be paid out of Capital Project Funds |
|
|
Recommendation
|
Recommend approval of the Guaranteed Maximum Price (GMP) for the Electrical Package at Elementary School #16 as presented. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Leon Fisher - Executive Director |
|
Signed By: |
|
Michael McFarland - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Gary Grassia Moved, Member Kelicia Stevenson seconded to approve the Original motion 'Recommend approval of the Guaranteed Maximum Price (GMP) for the Electrical Package at Elementary School #16 as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0. | The motion Carried 6 - 0 | | | Mia Hall | Yes | Gary Grassia | Yes | LaTonya Mayfield | Yes | Nedra Robinson | Yes | Kelicia Stevenson | Yes | Daryl Davis | Yes | |
|
|
|
|
|
|